October 2022

On both buildings in the school district, large-scale design conversations are coming to a close as we focus on the operational and functional needs to make the designs work.

At the Middle/High School, the new front entrance canopy has been approved (see image below), the interior finishes have been selected, and conversations are ongoing on the selection of items such as door and glass types.

At the Elementary School, coordination on how the addition ties into the site and the existing infrastructure is ongoing as we understand how the addition is best to function. Like the Middle/High School, interior finishes have been selected at the Elementary School, and selection discussions, such as door types, roof types, etc., are ongoing.

WHAT’S NEXT?

  • Detailed conversations about power, lighting, plumbing fixtures, and other infrastructure items.

  • Engineering meetings with the Administration

  • Finalizing shop equipment layouts in the Tech Ed Department

High-Level Project Timeline

  • October 2, 2022: 75% Progress Plans

  • November 17, 2022: Drawings sent out for Bid

  • December 2022: Prebid Walk for Contractors interested in the project

  • January 2023: Project bids due